- Managing Agents: Money → Bills & Payments → Section 20 Consultations (
/management/section-20or/management/building/<buildingId>/section-20) - RTM / RMC Directors: Money → Service Charges → Section 20 Consultations (
/rtm/section-20or/rmc/section-20) - Homeowners / Leaseholders: Money → Section 20 Notices (
/leaseholder/section-20or/shareholder/section-20)
Statutory thresholds (England & Wales)
Manage.Management evaluates date-effective statutory rules for England & Northern Ireland (gb-eng-nir) and Wales (gb-wal) inclusive of VAT and professional fees (such as surveyor, structural engineer, or project management fees), apportioned across the relevant Service Charge Schedule:
The 9 plain-English consultation stages
Every Section 20 project moves through clear, plain-English statutory stages visible to managers, directors, and leaseholders:1
1. Planning and cost check (Draft)
Define the scope of works or agreement, link the target Service Charge Schedule, verify that schedule shares sum to 100%, and check whether estimated gross costs (including VAT and fees) exceed £250 / £100 for any flat.
2
2. First notice sent — Notice of Intention (30+ days)
Serve the Stage 1 Notice of Intention describing the proposed works/agreement, why they are needed, and inviting written leaseholder observations — plus contractor nominations where required — within a statutory minimum 30-day consultation window (allowing extra days for postal service).
3
3. Gathering contractor quotes (Estimates)
Log written leaseholder observations, approach compliant contractors (including valid leaseholder-nominated contractors where applicable), and collect at least two estimates (at least one wholly unconnected with the landlord/RMC/RTM).
4
4. Quotes shared with leaseholders — Notice of Estimates / Proposals (30+ days)
Serve the Stage 2 Statement of Estimates & Notice to Accompany summarising all estimates obtained, inspection arrangements, and responses to Stage 1 observations, opening a second 30-day written observation period.
5
5. Contractor chosen (Awarded)
Review all Stage 2 observations formally at board/agent level and record the contract award decision.
6
6. Reasons for choice sent (Within 21 days, when required)
If the chosen contractor did not submit the lowest estimate and was not a leaseholder nominee, serve the statutory Statement of Reasons within 21 days of entering into the contract, explaining the decision and summarising Stage 2 observations.
7
7. Consultation complete
All required notices, observation windows, and reasons have been satisfied. Linked major-works demands and supplier invoices pass the Section 20 statutory gate in Finance v2.
- 8. Tribunal dispensation — records First-tier Tribunal / LVT dispensation references where emergency works prevented advance consultation.
- 9. Cancelled — closes a consultation without contract award while preserving historical notices.
Locked plain-English audit trail & attestation
Once a statutory notice is served, it can never be silently edited or deleted:- Locked once sent: Served notices in Consultation history carry a Locked once sent badge enforced at the database layer (
Protected against edits). - Plain-English evidence rows: Every milestone, observation deadline, recipient batch, and board decision is rendered in clear plain English ready for director review, conveyancing (LPE1) packs, or tribunal bundles.
- Cryptographic fingerprinting (
etched.xyz): Each locked stage generates a deterministic SHA-256 evidence envelope (manage.section20.evidence.v1) for tamper-evident timestamp attestation.